3,650-tonne Power Socket Ready for Sea Voyage to the Borssele Wind Energy Area

March 21, 2020 | Renewables | Energy Facts Staff Writer | 3min

Grid transformer platform to be sailed out to sea on 22 March 2020.

The superstructure (topside) of TenneT’s offshore transformer platform for the Borssele III, IV and V wind area is ready for its sea voyage. Right on schedule, the offshore power socket, Borssele Beta, will provide access to the wind energy generated by the offshore wind farms Borssele III, IV and V that are still under construction, and bring it onshore starting in 2020.

The 700 MW offshore station is expected to be operational according to schedule on 1 September. From that point onwards, the wind farm being constructed approximately 22 km from the coast of the Province of Zeeland by the Blauwwind consortium will be plugged into this power socket. The electricity generated by the offshore Borssele III, IV and V wind farm will subsequently be brought onshore to the high voltage substation in Borssele by means of two 67-kilometre long cables. The platform was built by HSM Offshore in Schiedam (NL).

Marco Kuijpers, Director Offshore Projects: “With this platform, the offshore grid that TenneT is building in the Dutch North Sea is definitively taking shape. Borssele Beta is the second offshore grid connection built by TenneT. Over the coming eight years we will build a new offshore connection every year. I am proud that we are able to make such a significant contribution to the energy transition in which offshore wind energy plays a crucial role.”

Sandor Gaastra, DG Climate and Energy, Ministry of Economic Affairs and Climate Policy (EZK):“The construction of the Dutch wind farms in the North Sea is well on track. This is in part due to the coordinated construction of an offshore electricity grid by TenneT. The second ‘offshore power socket’ will transport approximately 2.5% of the electricity used in the Netherlands from the wind farm to the mainland.”

Sail-out
On the 22th of March, the pontoon carrying the topside will sail through the New Waterway in the direction of the Borssele III and IV wind area. At this site, a crane vessel will place the topside on top of the substructure (jacket).
The superstructure (topside) consists of three interior levels (main deck, utility deck, control deck) and an outer deck (roof deck). The topside is 25 metres high, 58 metres long and 32 metres wide. The topside weighs 3,650 tonnes.

Ecological and navigational monitoring station
The Borssele Beta transformer platform also contains a monitoring station with various monitoring systems, such as nautical radars, meteorological systems (for wind, precipitation, clouds and temperature) and ecological monitoring systems for birds and bats. A similar Maritime Information Provision Service Point (MIVSP) is being installed on every offshore transformer platform by the Directorate-General for Public Works and Water Management (Rijkswaterstaat) in cooperation with TenneT. These monitoring stations will be used to collect unique and detailed information along the entire Dutch coastal area. In addition to the Coastguard, other organisations, such as port authorities, universities, the Dutch Meteorological Office (KNMI), and wind farm operators will make use of this data.

Important step in energy transition
Forty percent of the Netherlands’ electricity supply will come from offshore wind farms by 2030. As such, offshore wind energy is an important pillar of the energy transition. The Netherlands is on track towards achieving its climate objectives. TenneT is making an important contribution to the energy transition by installing offshore wind farms on schedule and within budget. Borssele Alpha was delivered on time (September 2019) and Borssele Beta now also will be installed offshore on schedule to connect the wind farms that are now being constructed. The Borssele III and IV wind farms will have a total capacity of 700 megawatts (MW). This corresponds to the electricity generation requirements of approximately one million households. The power will be connected through TenneT’s offshore Borssele Beta connection to the Borssele high voltage substation, from which it will be distributed to the onshore grid. TenneT will connect the wind farms off the coast of the Zeeland, Zuid-Holland and Noord-Holland provinces and the area above the West Frisian Islands the same way. Eight times over, TenneT will use the same 700 MW transformer platforms that are located close to the wind farms, and the same type of cable connection to the coast. This standardisation will allow these projects to be completed more efficiently, more quickly and more economically.

9,600 MW wind
In addition to the 3.5 GW set out in the ‘Roadmap for offshore wind energy’ (2015), TenneT will connect another 6.1 GW of offshore wind energy to the Dutch high voltage grid in accordance with the ‘Roadmap for offshore wind energy 2030’ (2019). Up to and including 2026, TenneT will install eight standard alternating current (AC) connections, each with a capacity of 700 MW. Starting in 2027, larger wind farms will be built further away from the coast in the IJmuiden Far wind energy region. Given the large capacity (2 GW per connection), and to limit the loss of energy during transport, TenneT is installing this connection as a direct current (DC) connection.